[edit] Where in Project.net

Projects > Workplan > Properties > Change Working Times > New

[edit] Create Worktime Calendar

[edit] To create a Worktime Calendar

Create Working Time Calendar
Create Working Time Calendar

1. In the Change Working Times tab, click on the [New] option under Toolbox.

2. Enter the Calendar Name and click on [Submit].

3. In the Day of Week Setting page provide the required entries in the Day of week setting to define the working time and days of the week and click on [Submit].

4. The created calendar is now available in the list in the Change Working Times tab under the Working Time Calendars channel.

[edit] Toolbox

  • Blogit - Selecting this allows the user to create a blog entry for the creation of a Worktime Calendar.

[edit] Create Calendar Menu


Personal tools